Friday, July 7, 2017

Ansonia announces road work schedule

Sharing from the City of Ansonia Facebook page:
Notice to residents: Beginning Monday, July 10th, reclaiming, grading, and rolling will begin on the following streets designated for paving this phase. 

Schedule is subject to change:

10th - Spring Street, begin Bartholomew Avenue
11th - Continue Bartholomew, Hoinski Way
12th - Hoinski Way
13th - Hodio Drive
14th - Shortell Drive and Woodlawn Avenue Extension
Once this process is complete, the roads will be paved in the same order, starting the 17th through the 21st.